Projecten
|
Type |
Naam |
P(kW) |
Productie/j |
Start |
Investering |
|
Wind |
Eeklo |
1.800 |
3.250 MWh |
23.06.01 |
€1.760.000 |
|
Wind |
Eeklo |
1.800 |
3.250 MWh |
29.06.01 |
€1.760.000 |
|
Wind |
Eeklo |
600 |
950 MWh |
01.02.02 |
€570.000 |
|
Wind |
Gent (19,93%) |
4.385 |
8.800 MWh |
15.04.05 |
€5.250.000 |
|
Wind |
Gistel (33%) |
759 |
1.650 MWh |
10.05.07 |
€810.000 |
|
Waterkracht |
Rotselaar |
75 |
500 MWh |
01.07.04 |
€325.000 |
|
Waterkracht |
Overijse |
12 |
20 MWh |
28.06.03 |
€80.000 |
|
Biomassa |
Eeklo |
200 |
400 MWh |
28.12.06 |
€325.000 |
|
PV |
PV decentraal |
400 |
340 MWh |
01.06.07 |
€2.400.000 |
Projecten in ontwikkeling
|
Type |
Naam |
P(kW) |
Productie/j |
Start |
Investering |
|
Waterkracht |
Schoonhoven |
10 |
46 MWh |
06.11.09 |
€300.000 |
|
PV |
PV decentraal |
200 |
170 MWh |
€1.200.000 |
|
|
Wind |
Asse |
4.000 |
8.000 MWh |
€5.000.000 |
|
|
Wind |
Tournai |
4.600 |
10.000 MWh |
31.10.10 |
€6.000.000 |
|
Wind |
Schelle |
6.000 |
12.000 MWh |
€7.500.000 |
|
|
Wind |
Ninove |
8.000 |
16.000 MWh |
€10.000.000 |
|
|
Wind |
Halen |
11.500 |
20.000 MWh |
€15.000.000 |
Warm water?Na verwarming gaat het meeste energie naar warm water. Je moet dus opletten dat je geen warm water verspilt én dat je het water efficiënt opwarmt. |